Conn. Gen. Stat. § 20-423

Hearing on denial of certificate. Subsequent application

Known as the Home Improvement Act

The act spans §§ 20–20 (21 sections).

(P.A. 79-606, S. 6, 14; P.A. 88-269, S. 6; P.A. 98-3, S. 65.) History: P.A. 88-269 added Subsec

(a) Upon refusal to issue or renew a certificate, the commissioner shall notify the applicant of the denial and of the applicant's right to request a hearing within ten days from the date of receipt of the notice of denial.

(b) If the applicant requests a hearing within such ten days, the commissioner shall give notice of the grounds for the commissioner's refusal and shall conduct a hearing concerning such refusal in accordance with the provisions of chapter 54 concerning contested cases.

(c) If the commissioner's denial of a certificate is sustained after such hearing, an applicant may make new application not less than one year after the date on which such denial was sustained.

Official source: Connecticut General Assembly. Reproduced from public-domain Connecticut statutes; confirm against the official source for the current text. Not legal advice.