Not later than three months after approval of the Commissioner of Energy and Environmental Protection of mapping of aquifers at level B, each municipal aquifer protection agency authorized pursuant to section 22a-354o shall inventory land uses overlying the mapped zone of contribution and recharge areas of such aquifers in accordance with guidelines established by the commissioner pursuant to section 22a-354f . Such inventory shall be completed not more than one year after authorization of the agency.
Conn. Gen. Stat. § 22a-354e
Inventory of land uses overlying aquifers
Known as the Connecticut Water Diversion Policy Act
The act spans §§ 22–22 (112 sections).
(P.A. 88-324, S. 5; P.A. 89-305, S. 27, 32; P.A. 11-80, S. 1.) History: P.A. 89-305 required inventory to be completed within a year of agency authorization and made technical c…
Official source: Connecticut General Assembly. Reproduced from public-domain Connecticut statutes; confirm against the official source for the current text. Not legal advice.