Conn. Gen. Stat. § 22a-6q

Alternative time frame for action on permit

Known as the Environmental Protection Act

The act spans §§ 22–22 (122 sections).

(P.A. 95-218, S. 21, 24; P.A. 96-118, S. 1; P.A. 10-158, S. 4.) History: P.A. 95-218, S. 21 effective July 6, 1995; P.A. 96-118 made a technical correction to an internal refere…

When the commissioner determines, based on the size, novelty, complexity or technical difficulty of a project, that work cannot be completed within the schedule for timely action applicable to a permit application pursuant to subdivision (3) of subsection (b) of section 22a-6p , the commissioner shall notify the applicant of such determination within thirty days of receiving the permit application and shall, within forty-five days of providing such notice, establish an alternative permit schedule for timely action.

Official source: Connecticut General Assembly. Reproduced from public-domain Connecticut statutes; confirm against the official source for the current text. Not legal advice.