The statement of claim shall set forth the names of the party claimant, the owner or reputed owner of the structure or bridge, the contractor and the kind of labor done and whether the contract was with the owner or the owner’s agent or with the contractor, the sum claimed to be due, the time when the labor was commenced and finished, the location of such structure or bridge, the ground upon which the same is situated, and a description sufficient to identify the same.
Del. Code tit. 25, § 2733
Requirements of statement of claim
16 Del
Official source: Delaware Code Online. Reproduced from public-domain Delaware statutes; confirm against the official source for the current text. Not legal advice.