Del. Code tit. 26, § 910

Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, § 2]

85 Del

No county shall deny a conditional use permit to any electrical substation, along with any directly related project infrastructure, proposed to be located on unincorporated land within such county where the following conditions apply:

(1) The substation is being proposed to support the operation of a proposed renewable energy generation project of 250 MW or greater;

(2) The proposed substation would be located in a heavy industrial zone;

(3) An electrical substation is an allowed conditional use within the proposed zone; and

(4) The specific zoning district in which the proposed substation would be located already has an electric substation located in such zone with a rating of 230kv or greater as of August 3, 2023.