No construction contract may permit the withholding of retainage from any payment in excess of the amounts permitted in this Section. A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.
815 ILCS 603/20
Retainage
Known as the Contractor Prompt Payment Act
The act spans §§ 815-603-1 to 815-603-99 (6 sections).
P.A. 101-432, eff. 8-20-19.
Official source: Illinois General Assembly. Reproduced from public-domain Illinois statutes; confirm against the official source for the current text. Not legal advice.