Sec. 43. (a) If the surveyor is unable to let a contract and construct the proposed improvement for the estimated cost of construction, the surveyor shall report the fact to the court.

(b) The court shall immediately order a new assessment of benefits and damages if requested in writing by at least two-thirds (2/3) of the original petitioners.

(c) If the order for a new assessment is made:

(1) the procedure provided for following the making of the original assessment shall be followed with respect to the new assessment and subsequent actions; and

(2) the landowners have the same right to remonstrate and appeal as is provided for original assessments.