Ind. Code § 36-9-40-8

Filing of cost estimate by county engineer; limitation on entry into contract

As added by P.L.7-2002, SEC.1.

Sec. 8. (a) At least ten (10) days before the date fixed for a hearing under section 7 of this chapter, the engineer of the county shall file with the works board an estimate of the maximum cost of construction of the system proposed by the works board.

(b) A county may not enter into a contract under the preliminary resolution if the contract exceeds the engineer's estimate filed under subsection (a).

Official source: Indiana General Assembly. Reproduced from public-domain Indiana statutes; confirm against the official source for the current text. Not legal advice.