Ind. Code § 8-1-40-15

Electricity supplier's duty to procure customers' excess distributed generation; amounts credited to customers to be recognized in fuel adjustment proceedings

As added by P.L.264-2017, SEC.6.

Sec. 15. An electricity supplier shall procure the excess distributed generation produced by a customer at a rate approved by the commission under section 17 of this chapter. Amounts credited to a customer by an electricity supplier for excess distributed generation shall be recognized in the electricity supplier's fuel adjustment proceedings under IC 8-1-2-42.

Official source: Indiana General Assembly. Reproduced from public-domain Indiana statutes; confirm against the official source for the current text. Not legal advice.