Ind. Code § 8-1-40-19

Electricity supplier's petition to commission for recovery of energy delivery costs attributable to distributed generation customers; approval; findings by commission

As added by P.L.264-2017, SEC.6.

Sec. 19. (a) To ensure that customers that produce distributed generation are properly charged for the costs of the electricity delivery system through which an electricity supplier:

(1) provides retail electric service to those customers; and

(2) procures excess distributed generation from those customers;

the electricity supplier may request approval by the commission of the recovery of energy delivery costs attributable to serving customers that produce distributed generation.

(b) The commission may approve a request for cost recovery submitted by an electricity supplier under subsection (a) if the commission finds that the request:

(1) is reasonable; and

(2) does not result in a double recovery of energy delivery costs from customers that produce distributed generation.

Official source: Indiana General Assembly. Reproduced from public-domain Indiana statutes; confirm against the official source for the current text. Not legal advice.