La. R.S. 38:2189.1

Prescription; claims by contractors; surety

Known as the Local Government Equipment-Lease-Purchase Act

The act spans §§ 38–38 (168 sections).

Added by Acts 1982, No. 544, §1.

Any action by the contractor on the contract or on the bond, or by the contractor or the surety or both on the bond furnished by the contractor, against the state, or any of its agencies, boards or subdivisions, all in connection with the construction, alteration, or repair of any public works let by the state or any of its agencies, boards, or subdivisions, shall prescribe five years from the completion, the substantial completion, as defined in R.S. 38:2241.1, or acceptance of such work, whichever occurs first, or of notice of default of the contractor or other termination of the contract, unless otherwise limited in this Chapter. Any action which would be extinguished by the provisions of this Section may be brought within one year of the effective day of this Section.

Official source: Louisiana State Legislature. Reproduced from public-domain Louisiana statutes; confirm against the official source for the current text. Not legal advice.