Public-domain · open source
OpenJurist

Me. Rev. Stat. tit. 35-A, § 3492

Prohibition

PL 2021, c. 151, §1 (NEW)

A person may not construct, cause to be constructed or operate a solar energy development with ground-mounted solar panels occupying 3 or more acres without first obtaining approval of a decommissioning plan from the environmental permitting entity under section 3495.

Official source: Maine Legislature. Reproduced from public-domain Maine statutes; confirm against the official source for the current text. Not legal advice.