Public-domain · open source
OpenJurist

Me. Rev. Stat. tit. 35-A, § 3497

Applicability

PL 2023, c. 215, §2 (NEW).

This chapter applies to a solar energy development with ground-mounted solar panels occupying 3 or more acres on which construction begins on or after October 1, 2021 and to any other solar energy development with ground-mounted solar panels occupying 3 or more acres that undergoes a transfer of ownership on or after October 1, 2021.

Official source: Maine Legislature. Reproduced from public-domain Maine statutes; confirm against the official source for the current text. Not legal advice.