This chapter applies to a solar energy development with ground-mounted solar panels occupying 3 or more acres on which construction begins on or after October 1, 2021 and to any other solar energy development with ground-mounted solar panels occupying 3 or more acres that undergoes a transfer of ownership on or after October 1, 2021.
Me. Rev. Stat. tit. 35-A, § 3497
Applicability
PL 2023, c. 215, §2 (NEW).