Public-domain · open source
OpenJurist

Mich. Comp. Laws § 460.1157

Construction of transmission line not prohibited

Applied in 1 court decision — leading case 298 Mich. App. 338 - In re International Transmission Co. (2012)

Most recently applied in 298 Mich. App. 338 - In re International Transmission Co. (November 2012)

2008, Act 295, Imd

Sec. 157. This part does not prohibit an electric utility, affiliated transmission company, or independent transmission company from constructing a transmission line without obtaining an expedited siting certificate.

Official source: Michigan Legislature. Reproduced from public-domain Michigan statutes; confirm against the official source for the current text. Not legal advice.