Sec. 2. No public utility shall hereafter begin the construction or operation of any public utility plant or system thereof nor shall it render any service for the purpose of transacting or carrying on a local business either directly, or indirectly, by serving any other utility or agency so engaged in such local business, in any municipality in this state where any other utility or agency is then engaged in such local business and rendering the same sort of service, or where such municipality is receiving service of the same sort, until such public utility shall first obtain from the commission a certificate that public convenience and necessity requires or will require such construction, operation, service, or extension.
Mich. Comp. Laws § 460.502
Certificate of convenience; necessity for gas or electric utilities
Applied in 8 court decisions — leading case Attorney General v. Michigan Public Service Commission (1982)
Most recently applied in 268 Mich. App. 521 - Midwest Energy Cooperative v. Public Service Commission (January 2006)
1929, Act 69, Imd
How often courts cite this section
Court decisions citing this, by year. The dip in the last several years is a data-coverage gap, not a real trend — our corpus holds fewer opinions from the most recent years, so recent citations are undercounted.
Official source: Michigan Legislature. Reproduced from public-domain Michigan statutes; confirm against the official source for the current text. Not legal advice.