Sec. 5. An electric utility, affiliated transmission company, or independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under section 4 until the commission issues a certificate for that transmission line. Except as otherwise provided in section 9, a certificate of public convenience and necessity under this act is not required for constructing a new transmission line other than a major transmission line or for reconstructing, repairing, replacing, or improving an existing transmission line, including the addition of circuits to an existing transmission line.
Mich. Comp. Laws § 460.565
Transmission line; certificate required
Applied in 2 court decisions — leading case 298 Mich. App. 338 - In re International Transmission Co. (2012)
Most recently applied in In Re APPLICATION OF MICHIGAN ELECTRIC TRANSMISSION CO (November 2014)
1995, Act 30, Imd
Official source: Michigan Legislature. Reproduced from public-domain Michigan statutes; confirm against the official source for the current text. Not legal advice.