Sec. 3a. If a protracted public land survey corner is monumented by a surveyor, or if a previously monumented protracted public land survey corner is used by a surveyor, not more than 90 days after the protracted public land survey corner is monumented or used, the surveyor shall complete, sign, seal, and file with the register of deeds of the county where the protracted public land survey corner is situated a land corner recordation certificate for the protracted public land survey corner, unless the protracted public land survey corner monument and its accessories are as described in an existing land corner recordation certificate that has been filed under this act.
Mich. Comp. Laws § 54.203a
Protracted public land survey corner; completion and filing of land corner recordation certificate
Add. 2014, Act 420, Imd
Official source: Michigan Legislature. Reproduced from public-domain Michigan statutes; confirm against the official source for the current text. Not legal advice.