The use of either the design-build method of project delivery as provided in Section 31-7-13.1 or the construction manager at risk method of project delivery as provided in Section 31-7-13.2 must comply with the provisions of Section 31-5-51.
Miss. Code Ann. § 31-5-52
Performance and payment bonds required when using design-build or construction manager at risk methods of project delivery
Laws, 2007, ch. 494, § 3, eff from and after July 1, 2007.
Current official text: Mississippi Code (LexisNexis). Digitized from the UniCourt Code Improvement Commission public-domain capture. Reproduced from public-domain Mississippi statutes; confirm against the official source for the current text. Not legal advice.