(1) This part does not authorize a governmental body to:

(a) construct, own, or operate electricity distribution or transmission facilities; or

(b) use the proceeds from bonds under this part to construct, own, or operate electricity distribution or transmission facilities.

(2) Subsections (1)(a) and (1)(b) do not apply to electrical lines connecting component parts within the perimeter of an electric generation facility or to a dedicated tie line between an electric generation facility and the transmission grid or the point of use by the governmental body.

Official source: Montana Code Annotated (Montana Legislature). Reproduced from public-domain Montana statutes; confirm against the official source for the current text. Not legal advice.