A controversy arising out of a contract for the construction or repair of a highway entered by the director must be submitted to arbitration under this chapter and chapter 32-29.2. A person that voluntarily enters a contract for the construction or repair of a highway is deemed to have agreed to arbitration of a controversy arising out of that contract. For a claim for less than one hundred thousand dollars, only one arbitrator may be jointly selected by the parties. For a claim for one hundred thousand dollars or more, three persons comprise the arbitration board.
N.D. Cent. Code § 24-02-26
Controversies to be arbitrated - Arbitrators - How named
Official source: North Dakota Legislative Branch. Reproduced from public-domain North Dakota statutes; confirm against the official source for the current text. Not legal advice.