An electric public utility shall submit integrated resource plans to the commission. The commission may adopt rules and regulations for preparation and submission of integrated resource plans. At the request of the commission, the applicant shall pay a fee reasonably necessary for completing an investigation of the integrated resource plan up to an amount not exceeding two hundred fifty thousand dollars. If additional funds are reasonably necessary to pay the costs of an investigation of the integrated resource plan, upon request of the commission and with the approval of the emergency commission, the applicant shall pay such additional fees as are reasonably necessary for completion of an investigation by the commission.
N.D. Cent. Code § 49-05-04.4
Integrated resource plan
Official source: North Dakota Legislative Branch. Reproduced from public-domain North Dakota statutes; confirm against the official source for the current text. Not legal advice.