Other pipelines - Commission approval required

Upon construction of the southwest pipeline project, utilities, corporations, limited liability companies, companies, or any other person or entity which proposes to install or construct a pipeline or other underground conveyance system which crosses or intersects the southwest pipeline project may do so only with the approval of the commission, in accordance with the requirements and conditions imposed by the commission for the pipeline or other crossing.