Neb. Rev. Stat. § 39-2820

Contracting agency; cost estimate; conduct contract negotiations

Laws 2016, LB960, § 20; Laws 2019, LB583, § 14.

(1) Before the construction manager begins any construction services, a contracting agency shall: (a) Conduct an independent cost estimate for the project; and (b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services. (2) If the construction manager and the contracting agency are unable to negotiate a contract, the contracting agency may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the contracting agency shall be eligible to compete in the other contract procurement processes.

Official source: Nebraska Legislature. Reproduced from public-domain Nebraska statutes; confirm against the official source for the current text. Not legal advice.