In the event the substructure of such bridges or approaches is wholly or in part of iron, steel or other metal, the contract for the portion of the substructure to be built of iron, steel or other metal shall be let at a specified sum per lineal foot for tubing, and at a specified sum per pound for all other metal in place.
Neb. Rev. Stat. § 39-814
Bridge construction; yearly contracts; metal substructures; terms
Laws 1905, c. 126, § 4, p. 540; R.S.1913, § 2959; C.S.1922, § 2717; C.S.1929, § 39-804; R.S.1943, § 39-814.
Official source: Nebraska Legislature. Reproduced from public-domain Nebraska statutes; confirm against the official source for the current text. Not legal advice.