Limitation on Expenditures

Applied in 1 court decision — leading case Cersosimo v. Town of Townshend (1981)

Most recently applied in Cersosimo v. Town of Townshend (June 1981)

Source. 1953, 184:3

I. The total amount that may be expended on any bridge under this subdivision for the above purpose shall in no instance exceed the estimated sum that might be necessary for the construction or reconstruction of a bridge under RSA 234:4, 10 and 11.

II. The commissioner of transportation may waive the requirement for a new covered bridge that replaces a covered bridge which was destroyed within the previous 5 years of application under RSA 234:5.