Time of commencement and completion of sewerage system

Amended by L.1962, c. 198, s. 162.

Every sewerage company organized under the laws of this State shall commence the construction of the proposed system of sewerage within 6 months from the date of its organization, and shall complete the same within 3 years from the date of commencement. The conditions annexed to the consent of the corporate authorities may designate a shorter period for the completion of such works.