Three (3) months after the debt for which the lien is claimed becomes due, the lien claimant may enforce such lien by either a suit to foreclose the lien or by a sale as hereinafter provided.
§ 48-3-25 NMSA 1978
Enforcement of lien
1941 Comp., § 63-320, enacted by Laws 1953, ch. 125, § 4; 1953 Comp., § 61-3-23.
Official source: NMOneSource (New Mexico Compilation Commission). Reproduced from public-domain New Mexico statutes; confirm against the official source for the current text. Not legal advice.