NRS 108.22116

“Completion of the work of improvement” defined

Known as the Uniform Federal Lien Registration Act

The act spans §§ 108–108 (195 sections).

Applied in 1 court decision — leading case DYKEMA VS. DEL WEBB COMMUNITIES, INC. (2016)

Most recently applied in DYKEMA VS. DEL WEBB COMMUNITIES, INC. (December 2016)

(Added to NRS by 2003, 2587)

“Completion of the work of improvement” means:

1. The occupation or use by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement;

2. The acceptance by the owner, an agent of the owner or a representative of the owner of the work of improvement, accompanied by the cessation of all work on the work of improvement; or

3. The cessation of all work on a work of improvement for 30 consecutive days, provided a notice of completion is timely recorded and served and the work is not resumed under the same contract.

Official source: Nevada Legislature. Reproduced from public-domain Nevada statutes; confirm against the official source for the current text. Not legal advice.