Notice of right to lien: Form; service; effect

Known as the Uniform Federal Lien Registration Act

The act spans §§ 108–108 (195 sections).

Applied in 9 court decisions — leading case Hardy Companies, Inc. v. SNMARK, LLC (2010)

Most recently applied in Bd of Trustees Glazing Health v. Shannon Chambers (September 2018)

(Added to NRS by 1965, 1169; A 1967, 1104; 1969, 730; 1979, 1091; 1997, 2695; 2003, 2616; 2005, 1912; 2015, 1932; 2017, 1210)

How often courts cite this section

1986199020002010201820
citing decisions per year

Court decisions citing this, by year. The dip in the last several years is a data-coverage gap, not a real trend — our corpus holds fewer opinions from the most recent years, so recent citations are undercounted.

1. Except as otherwise provided in subsection 5, every lien claimant, other than one who performs only labor or is a potential claimant under NRS 608.150, who claims the benefit of NRS 108.221 to 108.246, inclusive, shall, at any time after the first delivery of material or performance of work or services under a contract, deliver in person or by certified mail to the owner of the property a notice of right to lien in substantially the following form:

A subcontractor or equipment or material supplier who gives such a notice must also deliver in person or send by certified mail a copy of the notice to the prime contractor for information only. The failure by a subcontractor to deliver the notice to the prime contractor is a ground for disciplinary proceedings against the subcontractor under chapter 624 of NRS but does not invalidate the notice to the owner.

2. Such a notice does not constitute a lien or give actual or constructive notice of a lien for any purpose.

3. No lien for materials or equipment furnished or for work or services performed, except labor, may be perfected or enforced pursuant to NRS 108.221 to 108.246, inclusive, unless the notice has been given.

4. The notice need not be verified, sworn to or acknowledged.

5. A prime contractor or other person who contracts directly with an owner or sells materials directly to an owner is not required to give notice pursuant to this section.

6. A lien claimant who is required by this section to give a notice of right to lien to an owner and who gives such a notice has a right to lien for materials or equipment furnished or for work or services performed in the 31 days before the date the notice of right to lien is given and for the materials or equipment furnished or for work or services performed anytime thereafter until the completion of the work of improvement.

Official source: Nevada Legislature. Reproduced from public-domain Nevada statutes; confirm against the official source for the current text. Not legal advice.