The plaintiff must, within 30 days after final judgment, pay the sum of money assessed. If the plaintiff is a railroad company, it shall also execute to the defendant a bond, with sureties to be determined and approved by the court or judge, conditioned that the plaintiff shall build proper fences through any enclosed field before commencing actual construction. In an action on the bond all damages sustained and the cost of the construction of such fences and cattle guards, with a reasonable attorney fee, to be fixed by the court, may be recovered.
NRS 37.140
Damages to be paid within 30 days after judgment; bond for railroad fence
Applied in 2 court decisions — leading case Valley Electric Ass'n v. Overfield (2005)
Most recently applied in Gold Ridge Partners v. Sierra Pacific Power Co. (September 2012)
[1911 CPA § 677; RL § 5619; NCL § 9166]
Official source: Nevada Legislature. Reproduced from public-domain Nevada statutes; confirm against the official source for the current text. Not legal advice.