Public-domain · open source
OpenJurist

NRS 704.891

Reports to be filed with Commission by person holding permit who is not public utility

Known as the Utility Environmental Protection Act

The act spans §§ 704–704 (414 sections).

(Added to NRS by 1985, 2297; A 1997, 1917; 2001, 2989)

1. Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

(a) The location, nature and capacity of that facility;

(b) The anticipated date for commercial operation of that facility;

(c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

(d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

2. The reports required by subsection 1 must be filed:

(a) On or before the date on which construction of a utility facility is commenced; and

(b) On a date not later than:

(1) Twelve months before the scheduled date of commercial operation of that facility; or

(2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.

Official source: Nevada Legislature. Reproduced from public-domain Nevada statutes; confirm against the official source for the current text. Not legal advice.