Before issuing a site certificate for a nuclear-fueled thermal power plant, the Energy Facility Siting Council must find that an adequate repository for the disposal of the high-level radioactive waste produced by the plant has been licensed to operate by the appropriate agency of the federal government. The repository must provide for the terminal disposition of such waste, with or without provision for retrieval for reprocessing.
ORS 469.595
Known as the Oregon Residential Energy Conservation Act
The act spans §§ 469–469 (299 sections).
Applied in 1 court decision — leading case Portland General Electric Co. v. Roberts (1985)
Most recently applied in Portland General Electric Co. v. Roberts (October 1985)
1981 c.1 §3
Official source: Oregon State Legislature. Reproduced from public-domain Oregon statutes; confirm against the official source for the current text. Not legal advice.