Public-domain · open source
OpenJurist

12 Pa.C.S. § 4305

Scope of work

(July 7, 2022, P.L.470, No.43, eff. 60 days)

(a) Requirement.--A program shall require for each proposed clean energy project and water conservation project a scope of work, energy baseline or water usage baseline and the projected energy savings or water usage reductions in order to establish the viability of the qualified project and the projected energy savings or water usage reductions.

(b) Verification of completion.--After a qualified project is completed, the municipality or county shall obtain verification from the qualifying commercial property owner and from an independent professional inspector or building code official that the qualified project was properly completed.

Official source: Pennsylvania General Assembly. Reproduced from public-domain Pennsylvania statutes; confirm against the official source for the current text. Not legal advice.