The failure of the planning commission to act within sixty-five days from and after the date of official submission to it under the provisions of § 11-2-24, shall be deemed approval, unless a longer period be granted by the board or other submitting official.
S.D. Codified Laws § 11-2-24.1
Approval by failure of planning commission to act in time--Exception if longer period granted
Applied in 1 court decision — leading case Hauck v. Clay County Commission (2023)
Most recently applied in Hauck v. Clay County Commission (August 2023)
Source: SL 1975, ch 113, § 14.
Official source: South Dakota Legislature. Reproduced from public-domain South Dakota statutes; confirm against the official source for the current text. Not legal advice.