The lien may be foreclosed at any time after sixty days from the date of furnishing the last item. The foreclosure may be conducted according to the provisions of chapter 21-53 or according to the provisions of chapter 21-54, subject to the right of persons adversely interested to require foreclosure under chapter 21-53.
S.D. Codified Laws § 44-11-4
Foreclosure of mechanics', laborers', and materialmen's liens--Action or advertisement
Source: SL 1925, ch 216, § 1; SL 1927, ch 160, § 1; SDC 1939, § 39.0804.
Official source: South Dakota Legislature. Reproduced from public-domain South Dakota statutes; confirm against the official source for the current text. Not legal advice.