Notwithstanding any other provision of this chapter, the commission may approve a tariff mechanism for the automatic annual adjustment of charges for the jurisdictional costs of new or modified transmission facilities with a design capacity of thirty-four and one-half kilovolts or more and which are more than five miles in length. For the purposes of §§49-34A-25.1 to 49-34A-25.4, inclusive, electric transmission facilities and electric transmission lines covered by this section include associated facilities such as substations and transformers.
S.D. Codified Laws § 49-34A-25.1
Approval of tariff mechanisms for automatic annual adjustment of charges for jurisdictional costs of new or modified transmission facilities
Source: SL 2006, ch 239, § 1.
Official source: South Dakota Legislature. Reproduced from public-domain South Dakota statutes; confirm against the official source for the current text. Not legal advice.