Within seven months after the application is filed the local review committee shall file a final report with the Public Utilities Commission which includes the recommendations of the committee as to mitigation measures and minority reports.
S.D. Codified Laws § 49-41B-10
Final report of committee
Known as the South Dakota Energy Facility Permit Act
The act spans §§ 49–49 (66 sections).
Applied in 1 court decision — leading case In Re Otter Tail Power Co. Ex Rel. Big Stone II (2008)
Most recently applied in In Re Otter Tail Power Co. Ex Rel. Big Stone II (January 2008)
Source: SL 1977, ch 390, § 13.
Official source: South Dakota Legislature. Reproduced from public-domain South Dakota statutes; confirm against the official source for the current text. Not legal advice.