Trans-state transmission facility--Permit and legislative approval required

Known as the South Dakota Energy Facility Permit Act

The act spans §§ 49–49 (66 sections).

Applied in 1 court decision — leading case 513 F. Supp. 257 - Citizens & Landowners v. Secretary, United States Department of Energy (1981)

Most recently applied in 513 F. Supp. 257 - Citizens & Landowners v. Secretary, United States Department of Energy (May 1981)

Source: SL 1979, ch 318, §§ 3, 5; SL 1980, ch 327, § 4.

No utility shall begin construction of a trans-state transmission facility within the state without first having obtained a permit as required in this chapter and approval by an act of the South Dakota Legislature.