Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests

Known as the South Dakota Energy Facility Permit Act

The act spans §§ 49–49 (66 sections).

Applied in 1 court decision — leading case In Re Otter Tail Power Co. Ex Rel. Big Stone II (2008)

Most recently applied in In Re Otter Tail Power Co. Ex Rel. Big Stone II (January 2008)

Source: SL 1977, ch 390, § 5; SL 2006, ch 242, § 2

A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11. A prefiling conference may be requested by the applicant and such request shall be granted by the commission.

Official source: South Dakota Legislature. Reproduced from public-domain South Dakota statutes; confirm against the official source for the current text. Not legal advice.