Public-domain · open source
OpenJurist

Tenn. Code Ann. § 54-5-122

Full settlement with contractor

Applied in 1 court decision — leading case Thompson v. Commissioner (1985)

Most recently applied in Thompson v. Commissioner (April 1985)

Acts 1917, ch. 74, § 6; Shan., § 1720a29b30 (p. 6551); Shan

The department may close a project after the following have occurred:

(1) The department shall provide thirty (30) days notice in some newspaper published in the county where the work is done, if there is a newspaper published there, and if not, in a newspaper in an adjoining county, that final settlement is about to be made and notifying all claimants to file notice of their claims with the department and the contractor's surety. The period for filing a notice of claim shall not be less than thirty (30) days after the last published notice. No notice of claim shall be valid unless it is verified by oath and filed after the publication of the first notice; and

(2) The contractor shall furnish evidence to satisfy the department that all the material used by the contractor, its subcontractors or its agents has been fully paid for and all laborers and other employees working for the contractor, its subcontractors or its agents have been fully paid.

Current official text: Tennessee Code (LexisNexis). Digitized from the UniCourt Code Improvement Commission public-domain capture. Reproduced from public-domain Tennessee statutes; confirm against the official source for the current text. Not legal advice.