A successor in interest to a permit holder may continue the surface coal mining and reclamation plan of the original permit holder until the successor's application is granted or denied if the successor:

(1) applies for a new permit not later than the 30th day after the date the person succeeds to the interest; and

(2) is able to obtain the same bond coverage as the original permit holder.