PROMPT PAY REQUIRED

Applied in 11 court decisions — leading case Mirta Zorrilla v. Aypco Construction II, LLC and Jose Luis Munoz (2015)

Most recently applied in Vast Construction, LLC v. CTC Contractors, LLC (July 2017)

Added by Acts 1993, 73rd Leg., ch. 479, Sec. 1, eff

How often courts cite this section

199820002010201710
citing decisions per year

Court decisions citing this, by year. The dip in the last several years is a data-coverage gap, not a real trend — our corpus holds fewer opinions from the most recent years, so recent citations are undercounted.

(a) If an owner or a person authorized to act on behalf of the owner receives a written payment request from a contractor for an amount that is allowed to the contractor under the contract for properly performed work or suitably stored or specially fabricated materials, the owner shall pay the amount to the contractor, less any amount withheld as authorized by statute, not later than the 35th day after the date the owner receives the request.

(b) A contractor who receives a payment under Subsection (a) or otherwise from an owner in connection with a contract to improve real property shall pay each of its subcontractors the portion of the owner's payment, including interest, if any, that is attributable to work properly performed or materials suitably stored or specially fabricated as provided under the contract by that subcontractor, to the extent of that subcontractor's interest in the owner's payment. The payment required by this subsection must be made not later than the seventh day after the date the contractor receives the owner's payment.

(c) A subcontractor who receives a payment under Subsection (b) or otherwise from a contractor in connection with a contract to improve real property shall pay each of its subcontractors the portion of the payment, including interest, if any, that is attributable to work properly performed or materials suitably stored or specially fabricated as provided under the contract by that subcontractor, to the extent of that subcontractor's interest in the payment. The payment required by this subsection must be made not later than the seventh day after the date the subcontractor receives the contractor's payment.