NOTICE TO LEGISLATORS OF COMPLETED PROJECTS

Acts 1995, 74th Leg., ch. 165, Sec. 1, eff

(a) Not later than the 10th day before the date on which a major road project is scheduled for completion, the department shall provide notice of the location and completion date of the road project to each member of the legislature who represents the county in which the road project is located and who wants to receive the notice.

(b) The department shall ask each legislator whether the legislator wants to receive notices under this section.

Official source: Texas Constitution and Statutes. Reproduced from public-domain Texas statutes; confirm against the official source for the current text. Not legal advice.