Utah Code § 38-1a-405

Preconstruction liens on equal footing

Enacted by Chapter 464, 2013 General Session

(1) Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of:

(a) when the claimant submitted the claimant's notice of preconstruction service for recording;

(b) when the claimant submitted the claimant's notice of preconstruction lien for recording; or

(c) when the preconstruction service related to the lien occurs.

(2) Subsection (1) does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.

Official source: Utah State Legislature. Reproduced from public-domain Utah statutes; confirm against the official source for the current text. Not legal advice.