Utah Code § 54-18-302

Public workshops

Enacted by Chapter 316, 2009 General Session

After a public utility files the notice of intent in accordance with Subsection 54-18-301(3) and before it files a land use application, the public utility shall:

(1) conduct informal public workshops at locations along the proposed corridor to provide information about:

(a) the high voltage power line; and

(b) the process for obtaining a land use permit; and

(2) provide notice of the public workshops at least 14 days before a public workshop to:

(a) a newspaper of general circulation in the target study area;

(b) radio stations in the target study area; and

(c) an affected entity.