Utah Code § 54-26-502

Operating requirements -- Registration suspension

Enacted by Chapter 318, 2025 General Session

(1) A large-scale generation provider that fails to satisfy the requirements of this chapter:

(a) may not initiate new service to a large load customer;

(b) shall remedy any deficiencies within 90 days after the day on which the deficiency arises; and

(c) may have reasonable conditions imposed by the commission on the provider's registration status.

(2) If the commission suspends or revokes a large-scale generation provider's registration:

(a) the provider may not continue to provide service to a large load customer after the large load customer has been given a reasonable opportunity to secure alternative service arrangements; and

(b) the large load customer may not receive electric service from another large-scale generation provider or a qualified electric utility except pursuant to agreement and commission approval of the terms of a new large load contract consistent with this chapter.