Retainage on construction contracts

Known as the Virginia Public Procurement Act

The act spans §§ 2–2 (104 sections).

Applied in 1 court decision — leading case Bell BCI Co. v. Old Dominion Demolition Corp. (2003)

Most recently applied in Bell BCI Co. v. Old Dominion Demolition Corp. (December 2003)

1982, c. 647, § 11-56; 2001, c. 844.

A. In any public contract for construction that provides for progress payments in installments based upon an estimated percentage of completion, the contractor shall be paid at least ninety-five percent of the earned sum when payment is due, with no more than five percent being retained to ensure faithful performance of the contract. All amounts withheld may be included in the final payment.

B. Any subcontract for a public project that provides for similar progress payments shall be subject to the provisions of this section.