State energy performance standard—Limit on early adoption incentive payments.

2022 c 177 s 5; 2019 c 285 s 5.

(1) The department may not issue a certification for a tier 1 incentive application under RCW 19.27A.220(8)(a) if doing so is likely to result in total incentive payments under RCW 19.27A.220(8)(a) in excess of $75,000,000.

(2) The department may not issue certification for a tier 2 incentive application under RCW 19.27A.220(8)(b) if doing so is likely to result in total incentive payments under RCW 19.27A.220(8)(b) in excess of $150,000,000.

Official source: Washington State Legislature. Reproduced from public-domain Washington statutes; confirm against the official source for the current text. Not legal advice.