RCW 4.24.360

Construction contract provision waiving, releasing, etc., rights of contractor, etc., to damages or adjustment for unreasonable delay caused by contractee, etc.—Declared void and unenforceable—Exceptions.

Applied in 9 court decisions — leading case 77 Wash. App. 137 - Absher Construction Co. v. Kent School District No. 415 (1995)

Most recently applied in SCOCCOLO CONST. v. City of Renton (October 2006)

1979 ex.s. c 264 s 1.

How often courts cite this section

19902000200620
citing decisions per year

Court decisions citing this, by year. The dip in the last several years is a data-coverage gap, not a real trend — our corpus holds fewer opinions from the most recent years, so recent citations are undercounted.

Any clause in a construction contract, as defined in RCW 4.24.370, which purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable.

This section shall not be construed to void any provision in a construction contract, as defined in RCW 4.24.370, which (1) requires notice of delays, (2) provides for arbitration or other procedure for settlement, or (3) provides for reasonable liquidated damages.