Public-domain · open source
OpenJurist

RCW 82.89.050

Requirements for recipients—Meaningful construction.

2022 c 185 s 5.

(1) The recipient of a deferral certificate under RCW 82.89.040 must begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate unless construction was delayed due to circumstances beyond the recipient's control. Lack of funding is not considered a circumstance beyond the recipient's control.

(2) If the recipient does not begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, the deferral certificate issued under RCW 82.89.040 is invalid and taxes deferred under this chapter are due immediately.

Official source: Washington State Legislature. Reproduced from public-domain Washington statutes; confirm against the official source for the current text. Not legal advice.